Quiz Summary
0 of 199 Questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 199 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- 81
- 82
- 83
- 84
- 85
- 86
- 87
- 88
- 89
- 90
- 91
- 92
- 93
- 94
- 95
- 96
- 97
- 98
- 99
- 100
- 101
- 102
- 103
- 104
- 105
- 106
- 107
- 108
- 109
- 110
- 111
- 112
- 113
- 114
- 115
- 116
- 117
- 118
- 119
- 120
- 121
- 122
- 123
- 124
- 125
- 126
- 127
- 128
- 129
- 130
- 131
- 132
- 133
- 134
- 135
- 136
- 137
- 138
- 139
- 140
- 141
- 142
- 143
- 144
- 145
- 146
- 147
- 148
- 149
- 150
- 151
- 152
- 153
- 154
- 155
- 156
- 157
- 158
- 159
- 160
- 161
- 162
- 163
- 164
- 165
- 166
- 167
- 168
- 169
- 170
- 171
- 172
- 173
- 174
- 175
- 176
- 177
- 178
- 179
- 180
- 181
- 182
- 183
- 184
- 185
- 186
- 187
- 188
- 189
- 190
- 191
- 192
- 193
- 194
- 195
- 196
- 197
- 198
- 199
- Current
- Review / Skip
- Answered
- Correct
- Incorrect
- Question 1 of 199
1. Question
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
CorrectIncorrect - Question 2 of 199
2. Question
Which tool or technique is required in order to determine the project budget?
CorrectIncorrect - Question 3 of 199
3. Question
What is the total float of the critical path?
CorrectIncorrect - Question 4 of 199
4. Question
When is a Salience Model used?
CorrectIncorrect - Question 5 of 199
5. Question
Which tools or techniques will a project manager use for Develop Project Team?
CorrectIncorrect - Question 6 of 199
6. Question
Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?
CorrectIncorrect - Question 7 of 199
7. Question
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
CorrectIncorrect - Question 8 of 199
8. Question
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
CorrectIncorrect - Question 9 of 199
9. Question
Expected monetary value (EMV) is computed by which equation?
CorrectIncorrect - Question 10 of 199
10. Question
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
CorrectIncorrect - Question 11 of 199
11. Question
What are the key components of the communication model?
CorrectIncorrect - Question 12 of 199
12. Question
Which process occurs within the Monitoring and Controlling Process Group?
CorrectIncorrect - Question 13 of 199
13. Question
When does Monitor and Control Risks occur?
CorrectIncorrect - Question 14 of 199
14. Question
The staffing management plan is part of the:
CorrectIncorrect - Question 15 of 199
15. Question
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?
CorrectIncorrect - Question 16 of 199
16. Question
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
CorrectIncorrect - Question 17 of 199
17. Question
Which document defines how a project is executed, monitored and controlled, and closed?
CorrectIncorrect - Question 18 of 199
18. Question
The Perform Quality Assurance p
CorrectIncorrect - Question 19 of 199
19. Question
A project manager should communicate to stakeholders about resolved project issues by updating the:
CorrectIncorrect - Question 20 of 199
20. Question
Based on the following metrics: EV=$20,000, AC=$22,000, and PV=$28,000, what is the project CV?
CorrectIncorrect - Question 21 of 199
21. Question
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
CorrectIncorrect - Question 22 of 199
22. Question
Which of the following is an output of Direct and Manage Project Execution?
CorrectIncorrect - Question 23 of 199
23. Question
In complex projects/ initiating processes should be completed:
CorrectIncorrect - Question 24 of 199
24. Question
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
CorrectIncorrect - Question 25 of 199
25. Question
The key benefit of the Monitoring and Controlling Process Group is the ability to:
CorrectIncorrect - Question 26 of 199
26. Question
Cost aggregation is typically performed by aggregating work packages in accordance with the:
CorrectIncorrect - Question 27 of 199
27. Question
Activity cost estimates are quantitative assessments of the probable costs required to:
CorrectIncorrect - Question 28 of 199
28. Question
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
CorrectIncorrect - Question 29 of 199
29. Question
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
CorrectIncorrect - Question 30 of 199
30. Question
Which is an input to the Verify Scope process?
CorrectIncorrect - Question 31 of 199
31. Question
Inputs to the Define Activities process include:
CorrectIncorrect - Question 32 of 199
32. Question
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
CorrectIncorrect - Question 33 of 199
33. Question
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?
CorrectIncorrect - Question 34 of 199
34. Question
In a typical project, project managers spend most of their time:
CorrectIncorrect - Question 35 of 199
35. Question
Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?
CorrectIncorrect - Question 36 of 199
36. Question
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
CorrectIncorrect - Question 37 of 199
37. Question
Funding limit reconciliation is a tool and technique used in which process?
CorrectIncorrect - Question 38 of 199
38. Question
Which standard examines an enterprise’s project management process capabilities?
CorrectIncorrect - Question 39 of 199
39. Question
An associate who calculates fees daily to support the department is doing which of the following?
CorrectIncorrect - Question 40 of 199
40. Question
Which tool or technique is used in the Plan Scope Management process?
CorrectIncorrect - Question 41 of 199
41. Question
Which type of graphic is displayed below?
CorrectIncorrect - Question 42 of 199
42. Question
Create WBS is part of which of the following Knowledge Areas?
CorrectIncorrect - Question 43 of 199
43. Question
Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?
CorrectIncorrect - Question 44 of 199
44. Question
In which process might you use risk reassessment as a tool and technique?
CorrectIncorrect - Question 45 of 199
45. Question
Which type of analysis would be used for the Plan Quality process?
CorrectIncorrect - Question 46 of 199
46. Question
In which domain of project management would a Pareto chart provide useful information?
CorrectIncorrect - Question 47 of 199
47. Question
Which of the following are inputs into the Administer Procurements process?
CorrectIncorrect - Question 48 of 199
48. Question
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
CorrectIncorrect - Question 49 of 199
49. Question
The process to ensure that appropriate quality standards and operational definitions are used is:
CorrectIncorrect - Question 50 of 199
50. Question
Scope, schedule, and cost parameters are integrated in the:
CorrectIncorrect - Question 51 of 199
51. Question
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
CorrectIncorrect - Question 52 of 199
52. Question
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
CorrectIncorrect - Question 53 of 199
53. Question
An input of the Create WBS process is:
CorrectIncorrect - Question 54 of 199
54. Question
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
CorrectIncorrect - Question 55 of 199
55. Question
In the basic communication model, which term refers to the method that is used to convey the message?
CorrectIncorrect - Question 56 of 199
56. Question
The process of developing a detailed description of the project and product is known as:
CorrectIncorrect - Question 57 of 199
57. Question
Which type of team can be defined as a group of people with a shared goal who fulfill their roles although spending little or no time meeting face to face?
CorrectIncorrect - Question 58 of 199
58. Question
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
CorrectIncorrect - Question 59 of 199
59. Question
What are assigned risk ratings based upon?
CorrectIncorrect - Question 60 of 199
60. Question
Which of the following factors is lowest at the start of the project?
CorrectIncorrect - Question 61 of 199
61. Question
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
CorrectIncorrect - Question 62 of 199
62. Question
Whose approval may be required for change requests after change control board (CCB) approval?
CorrectIncorrect - Question 63 of 199
63. Question
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
CorrectIncorrect - Question 64 of 199
64. Question
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
CorrectIncorrect - Question 65 of 199
65. Question
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
CorrectIncorrect - Question 66 of 199
66. Question
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
CorrectIncorrect - Question 67 of 199
67. Question
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
CorrectIncorrect - Question 68 of 199
68. Question
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
CorrectIncorrect - Question 69 of 199
69. Question
A risk may be graded into different priorities by which process?
CorrectIncorrect - Question 70 of 199
70. Question
The traditional organization chart structure that can be used to show positions and relationships in a graphic top-down format is called a:
CorrectIncorrect - Question 71 of 199
71. Question
What are the formal and informal policies, procedures, and guidelines that could impact how the project’s scope is managed?
CorrectIncorrect - Question 72 of 199
72. Question
Activities on the critical path have which type of float?
CorrectIncorrect - Question 73 of 199
73. Question
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
CorrectIncorrect - Question 74 of 199
74. Question
Which of the following is the correct network diagram for the table?
CorrectIncorrect - Question 75 of 199
75. Question
Which technique is commonly used for the Quantitative Risk Analysis activity?
CorrectIncorrect - Question 76 of 199
76. Question
The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:
CorrectIncorrect - Question 77 of 199
77. Question
An input of the Control Schedule process is the:
CorrectIncorrect - Question 78 of 199
78. Question
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
CorrectIncorrect - Question 79 of 199
79. Question
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
CorrectIncorrect - Question 80 of 199
80. Question
The following is a network diagram for a project. What is the critical path for the project?
CorrectIncorrect - Question 81 of 199
81. Question
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
CorrectIncorrect - Question 82 of 199
82. Question
Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?
CorrectIncorrect - Question 83 of 199
83. Question
An input to the Identify Stakeholders process is:
CorrectIncorrect - Question 84 of 199
84. Question
Organizational process assets can be divided into which of the following two categories?
CorrectIncorrect - Question 85 of 199
85. Question
Who is responsible for reviewing change requests and approving or rejecting the change requests?
CorrectIncorrect - Question 86 of 199
86. Question
Another name for an Ishikawa diagram is:
CorrectIncorrect - Question 87 of 199
87. Question
Which input provides suppliers with a clear set of goals, requirements, and outcomes?
CorrectIncorrect - Question 88 of 199
88. Question
Projects are authorized by which of the following individuals?
CorrectIncorrect - Question 89 of 199
89. Question
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
CorrectIncorrect - Question 90 of 199
90. Question
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
CorrectIncorrect - Question 91 of 199
91. Question
When does the project team determine which dependencies are discretionary?
CorrectIncorrect - Question 92 of 199
92. Question
Which can be used to determine whether a process is stable or has predictable performance?
CorrectIncorrect - Question 93 of 199
93. Question
Which Manage Communications tool or technique focuses on identifying and managing barriers?
CorrectIncorrect - Question 94 of 199
94. Question
Quality and credibility of the qualitative risk analysis process requires that different levels of the risk’s probabilities and impacts be defined is the definition of what?
CorrectIncorrect - Question 95 of 199
95. Question
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
CorrectIncorrect - Question 96 of 199
96. Question
The number of potential communication channels for a project with 5 stakeholders is:
CorrectIncorrect - Question 97 of 199
97. Question
How many Project Management Process Groups are there?
CorrectIncorrect - Question 98 of 199
98. Question
The Human Resource Management processes are:
CorrectIncorrect - Question 99 of 199
99. Question
Which of the following is an input to the Direct and Manage Project Execution process?
CorrectIncorrect - Question 100 of 199
100. Question
Perform Integrated Change Control is the process of:
CorrectIncorrect - Question 101 of 199
101. Question
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
CorrectIncorrect - Question 102 of 199
102. Question
The purpose of inspection in Perform Quality Control is to keep errors:
CorrectIncorrect - Question 103 of 199
103. Question
Which of the following is an output of the Information Distribution Process?
CorrectIncorrect - Question 104 of 199
104. Question
Which of the following statements correctly characterizes pull communication?
CorrectIncorrect - Question 105 of 199
105. Question
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
CorrectIncorrect - Question 106 of 199
106. Question
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
CorrectIncorrect - Question 107 of 199
107. Question
Resource calendars are included in the:
CorrectIncorrect - Question 108 of 199
108. Question
Which of the following is an example of schedule compression?
CorrectIncorrect - Question 109 of 199
109. Question
Which characteristic is unique to project work and does not apply to operational work?
CorrectIncorrect - Question 110 of 199
110. Question
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
CorrectIncorrect - Question 111 of 199
111. Question
Variance and trend analysis is a tool and technique used in which process?
CorrectIncorrect - Question 112 of 199
112. Question
The purpose of the Project Communications Management Knowledge Area is to:
CorrectIncorrect - Question 113 of 199
113. Question
Which of the following is a tool or technique used in the Determine Budget process?
CorrectIncorrect - Question 114 of 199
114. Question
Which Process Group’s purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?
CorrectIncorrect - Question 115 of 199
115. Question
The following is a network diagram for a project. The total float for the project is how many days?
CorrectIncorrect - Question 116 of 199
116. Question
Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
CorrectIncorrect - Question 117 of 199
117. Question
Which process determines the risks that may affect the project and documents their characteristics?
CorrectIncorrect - Question 118 of 199
118. Question
Projects can intersect with an organization’s operations at various points during the product life cycle such as
CorrectIncorrect - Question 119 of 199
119. Question
Which of the following is an input to Direct and Manage Project Execution?
CorrectIncorrect - Question 120 of 199
120. Question
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
CorrectIncorrect - Question 121 of 199
121. Question
What provides information regarding the ways people, teams, and organizational units behave?
CorrectIncorrect - Question 122 of 199
122. Question
Which process involves identifying and documenting the logical relationships between project activities?
CorrectIncorrect - Question 123 of 199
123. Question
Managing procurement relationships and monitoring contract performance are part of which process?
CorrectIncorrect - Question 124 of 199
124. Question
When cost variance is negative and schedule variance is positive, the project is:
CorrectIncorrect - Question 125 of 199
125. Question
What is the term assigned to products or services having the same functional use but different technical characteristics?
CorrectIncorrect - Question 126 of 199
126. Question
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
CorrectIncorrect - Question 127 of 199
127. Question
Risk categorization is a tool or technique used in which process?
CorrectIncorrect - Question 128 of 199
128. Question
An output of the Create WBS process is:
CorrectIncorrect - Question 129 of 199
129. Question
Which of the following are outputs of Develop Project Team?
CorrectIncorrect - Question 130 of 199
130. Question
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
CorrectIncorrect - Question 131 of 199
131. Question
Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?
CorrectIncorrect - Question 132 of 199
132. Question
Which Process Group typically consumes the bulk of a project’s budget?
CorrectIncorrect - Question 133 of 199
133. Question
Which of the following statements is true regarding project and product lifecycles?
CorrectIncorrect - Question 134 of 199
134. Question
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
CorrectIncorrect - Question 135 of 199
135. Question
Team performance assessments is an output of which of the following processes?
CorrectIncorrect - Question 136 of 199
136. Question
How is the schedule variance calculated using the earned value technique?
CorrectIncorrect - Question 137 of 199
137. Question
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
CorrectIncorrect - Question 138 of 199
138. Question
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
CorrectIncorrect - Question 139 of 199
139. Question
The primary benefit of the Plan Schedule Management process is that it:
CorrectIncorrect - Question 140 of 199
140. Question
An input used in developing the communications management plan is:
CorrectIncorrect - Question 141 of 199
141. Question
In the Plan Procurement Management process, which source selection criteria analyzes if the seller’s proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
CorrectIncorrect - Question 142 of 199
142. Question
Which of the following makes changes to formally control documentation to reflect modified or additional ideas or content?
CorrectIncorrect - Question 143 of 199
143. Question
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
CorrectIncorrect - Question 144 of 199
144. Question
Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks?
CorrectIncorrect - Question 145 of 199
145. Question
An output of the Create WBS process is:
CorrectIncorrect - Question 146 of 199
146. Question
Which of the following Project Communication Management processes uses performance reports as an input?
CorrectIncorrect - Question 147 of 199
147. Question
Which of the following can be used as an input for Define Scope?
CorrectIncorrect - Question 148 of 199
148. Question
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
CorrectIncorrect - Question 149 of 199
149. Question
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
CorrectIncorrect - Question 150 of 199
150. Question
When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?
CorrectIncorrect - Question 151 of 199
151. Question
Which of the following is an input to Control Scope?
CorrectIncorrect - Question 152 of 199
152. Question
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
CorrectIncorrect - Question 153 of 199
153. Question
Organizations manage portfolios based on which of the following types of plans?
CorrectIncorrect - Question 154 of 199
154. Question
The project manager for XYZ stationers is sequencing the activities for the project to set up a new office. It is known from knowledge of best practices that it is better to wait for the painters to finish painting the walls before the new floors are installed. This is an example of which of the following types of dependency?
CorrectIncorrect - Question 155 of 199
155. Question
Which of the following is a component of three-point estimates?
CorrectIncorrect - Question 156 of 199
156. Question
A car company authorized a project to build more fuel-efficient cars in response to gasoline shortages. With which of the following strategic considerations was this project mainly concerned?
CorrectIncorrect - Question 157 of 199
157. Question
What is the lowest level in the Work Breakdown Structure called?
CorrectIncorrect - Question 158 of 199
158. Question
Which of the following is an output from Control Scope?
CorrectIncorrect - Question 159 of 199
159. Question
The project manager has requested all expert team members to complete an anonymous questionnaire to identify possible risks. This is an example of a technique known as the:
CorrectIncorrect - Question 160 of 199
160. Question
Cost baseline is an output of which of the following processes?
CorrectIncorrect - Question 161 of 199
161. Question
A technique used to determine the cause and degree of difference between baseline and actual performance is:
CorrectIncorrect - Question 162 of 199
162. Question
As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?
CorrectIncorrect - Question 163 of 199
163. Question
The scope management plan and scope baseline are contained in:
CorrectIncorrect - Question 164 of 199
164. Question
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
CorrectIncorrect - Question 165 of 199
165. Question
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
CorrectIncorrect - Question 166 of 199
166. Question
Outputs from constituent processes might be used as
CorrectIncorrect - Question 167 of 199
167. Question
After Define Activities and Sequence Activities, the next process is:
CorrectIncorrect - Question 168 of 199
168. Question
Typical outcomes of a project include:
CorrectIncorrect - Question 169 of 199
169. Question
The project manager needs to review the templates in use. The templates are part of the:
CorrectIncorrect - Question 170 of 199
170. Question
What is the tool and technique used to request seller responses?
CorrectIncorrect - Question 171 of 199
171. Question
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
CorrectIncorrect - Question 172 of 199
172. Question
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
CorrectIncorrect - Question 173 of 199
173. Question
The total of the planned value (PV) is also known as:
CorrectIncorrect - Question 174 of 199
174. Question
An output of the Perform Integrated Change Control process is:
CorrectIncorrect - Question 175 of 199
175. Question
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
CorrectIncorrect - Question 176 of 199
176. Question
Which tool and technique of quality planning involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
CorrectIncorrect - Question 177 of 199
177. Question
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
CorrectIncorrect - Question 178 of 199
178. Question
Which risk response strategy is common for both positive and negative risks?
CorrectIncorrect - Question 179 of 199
179. Question
Who determines which dependencies are mandatory during the Sequence Activities process?
CorrectIncorrect - Question 180 of 199
180. Question
Which type of estimating is used to improve the accuracy of an activity’s duration?
CorrectIncorrect - Question 181 of 199
181. Question
A project manager who communicates to the project team though email is using which type of communication?
CorrectIncorrect - Question 182 of 199
182. Question
Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?
CorrectIncorrect - Question 183 of 199
183. Question
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
CorrectIncorrect - Question 184 of 199
184. Question
An output of the Plan Quality Management process is:
CorrectIncorrect - Question 185 of 199
185. Question
What happens to a stakeholder’s project influence over time?
CorrectIncorrect - Question 186 of 199
186. Question
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
CorrectIncorrect - Question 187 of 199
187. Question
The lowest level normally depicted in a work breakdown structure (WBS) is called a/an:
CorrectIncorrect - Question 188 of 199
188. Question
What are the identified risks for doing excessive decomposition in a WBS?
CorrectIncorrect - Question 189 of 199
189. Question
Inputs to the Plan Schedule Management process include:
CorrectIncorrect - Question 190 of 199
190. Question
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
CorrectIncorrect - Question 191 of 199
191. Question
Which of the following is a means of reaching a group decision in which everyone agrees on a single course of action?
CorrectIncorrect - Question 192 of 199
192. Question
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
CorrectIncorrect - Question 193 of 199
193. Question
Which of the following tools will be used to produce performance reports that provide information to stakeholders about project cost, schedule progress, and performance?
CorrectIncorrect - Question 194 of 199
194. Question
Which of the following is an input into the Develop Project Team process?
CorrectIncorrect - Question 195 of 199
195. Question
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
CorrectIncorrect - Question 196 of 199
196. Question
Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?
CorrectIncorrect - Question 197 of 199
197. Question
Which technique is utilized in the Control Schedule process?
CorrectIncorrect - Question 198 of 199
198. Question
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
CorrectIncorrect - Question 199 of 199
199. Question
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
CorrectIncorrect